Project Vision
This proposal outlines the design and construction of a full-scale **Water Upcycling Botanical Park**. This is not merely a utility; it is a landmark living ecosystem engineered to become a central feature of the resort. It will intercept and biologically transform 100% of the resort's wastewater into a source of life for a series of lush water gardens. The system integrates a final UV light treatment stage for tertiary polishing, ensuring the highest quality recycled water. This project will eliminate all pollution, create a water-secure and resilient resort, and establish a new global benchmark for regenerative tourism.
Full-Scale Design & Sizing
Investment Outline (Full Development)
| Component | Description | Cost (THB) | Cost (USD) |
|---|---|---|---|
| Design & Engineering | Full hydraulic, civil, and botanical design for large-scale system. | ฿ 450,000 | $ 12,300 |
| Site Prep & Earthworks | Land clearing and excavation for the 1,000 m² wetland cells. | ฿ 500,000 | $ 13,700 |
| Primary Treatment System | 75,000 L multi-chamber primary settling system. | ฿ 1,200,000 | $ 32,900 |
| Wetland Containment | High-quality, durable impermeable liner (EPDM/HDPE). | ฿ 1,500,000 | $ 41,100 |
| Bio-Filtration Media | 750 m³ of washed gravel and sand layers. | ฿ 1,500,000 | $ 41,100 |
| Plumbing & Connections | Extensive piping network for entire resort. | ฿ 600,000 | $ 16,400 |
| Botanical Layer | Native wetland plants for 1,000 m² area. | ฿ 375,000 | $ 10,300 |
| Labor & Installation | Skilled and unskilled labor for full construction. | ฿ 1,600,000 | $ 43,800 |
| Water Reuse System | High-capacity pump, large storage tanks, and distribution. | ฿ 375,000 | $ 10,300 |
| UV Light Treatment System | Commercial-grade UV disinfection unit for tertiary polishing. | ฿ 500,000 | $ 13,700 |
| Subtotal | ฿ 8,600,000 | $ 235,600 | |
| Contingency (15%) | ฿ 1,290,000 | $ 35,400 | |
| Total Estimated Investment | ฿ 9,890,000 | $ 271,000 |
Funding & Partnership Strategy
A Pathway to a Funded Project
We understand that this represents a significant investment. However, a project of this nature—demonstrating innovation in sustainable tourism, water conservation, and ecological restoration—is highly attractive to a variety of international and national grant-making bodies. The total project cost can be substantially offset through these programs.
AquaSai provides expert guidance in navigating the complex landscape of environmental and sustainable development grants. Our partnership extends beyond construction to help identify, apply for, and secure funding from sources including:
- International Environmental Conservation Funds
- National Sustainable Tourism Development Grants
- Private Philanthropic Foundations focused on Ocean Health
- Corporate Social Responsibility (CSR) Partnerships
Project Timeline (Full Development)
Phase 1: Design, Permitting & Grant Application
Weeks 1-6
Phase 2: Procurement & Logistics
Weeks 7-10
Phase 3: Earthworks & Construction
Weeks 11-22
Phase 4: Planting & System Seeding
Weeks 23-24
Phase 5: Commissioning & Monitoring
Weeks 25-28
Strategic Value & Return
Ecological Restoration
Permanently protects the coral reef by eliminating all nutrient pollution, reversing eutrophication, and securing the resort's primary natural asset for generations to come.
Water Independence
Creates 18.25 million liters of high-quality recycled water per year, ensuring total water security and resilience against drought and climate change.
A Destination Feature
The Botanical Park becomes a unique, beautiful, and educational attraction, enhancing the guest experience and providing a powerful storytelling asset for the resort.
World-Class Branding
Establishes the resort as a global leader in regenerative tourism, attracting high-value, eco-conscious travelers and generating significant positive press.
Operational Resilience
Future-proofs the entire resort against stricter environmental regulations, water scarcity, and rising operational costs, turning a liability into a productive asset.
Project Assumptions
- The resort will provide the required land area (~1,200 m²) for the system at no cost.
- The estimate assumes reasonable soil conditions and access for construction machinery.
- Costs for long-term operational maintenance (e.g., plant trimming, UV lamp replacement) are not included.
- Costs for major landscaping features (e.g., boardwalks, lighting) are not included but can be quoted separately.